January 74

1. Integral crew concept put in effect.

Hayyp New Year - Thanks, Thai brothers! You have threatened to withold contract gas supply. Lucky for us - cold showers are nice in 40 degree temperature!

2. Standardization and Training are moved back to building T-223 as part of reorganization of Operations. Safety and A&D remain at Building T-15.

9. Jolly Greens 30 & 60 launched from FOL at Ubon for F-4 crash 80 south of Ch 86. Two Knife birds (CH-53) in area make the pickup of (KNIVES 2, JOLLY G 0) Both Alpha & Bravo in good shape. Crews of 30 & 60

Jolly Green 30 Jolly Green 60

A/C McCormack A/C Nelson

CP Cerney CP Fagan

FM Shore FM

RS RS

RS RS

 